Color Kinetics Installation Checklist
Instructions for Completion. This was created to help minimize installation errors when installing Color Kinetics products. It is not an all-inclusive guide. Please review Installation Instructions a…
Instructions for Completion
- This was created to help minimize installation errors when installing Color Kinetics products. It is not an all-inclusive guide. Please review Installation Instructions and Specifications to ensure proper installation. Download Installation Checklist in .docx format. (if nothing happens, right-click and choose Open link in new tab to download).
- This checklist does not need to be returned to Signify upon completion.
- For bolded items below, please reference the Installation Requirements articles on the Color Kinetics Website.
- For questions or support regarding this checklist, please contact your Signify Color Kinetics representative.
Project Name:
Project Address (if address unavailable, please input site coordinates):
Pre-Installation Design
Task/Action....................................................... | Completion Date and Details............................. |
1. Assess environment and specific installation location to confirm suitable products are selected for site temperatures and environmental conditions. What is the maximum expected temperature to which products will be exposed? | |
2. Is product properly selected for site conditions/is installation near coastline (<3 miles) or in an otherwise corrosive area? What is the distance to the nearest coastline? | |
3. Assess installation for Ingress Protection requirements. Refer to IP66 Knowledge document for an overview of the IP66 rating. | |
4. Assess vibration environment and confirm suitable products are selected. | |
5. Check www.colorkinetics.com for any application notes. | |
6. Locate, read, and understand Installation Instructions at www.colorkinetics.com for each product being installed. | |
7. Evaluate fixture run lengths using the applicable Configuration Calculator. If input is needed, contact Color Kinetics for support. What is the longest run length of fixtures on this project? | |
8. Ensure site wiring plan does not contradict installation instructions. | |
9. Assess electrical surge protection and lightning protection requirements referencing the Surge Knowledge document. |
Installation
Tasks/Action....................................................... | Completion Date and Details............................. |
1. Follow and adhere to Installation Instructions for all products being installed. | |
2. Read and follow all safety warnings in the product Installation Instructions. | |
3. Keep end connectors free from dirt or contamination while stored awaiting installation. If product is being stored for extended periods of time, review the Long-Term Storage Guidance document. | |
4. Check www.colorkinetics.com for any firmware updates. | |
5. Follow all pertinent Electrical Codes during install. | |
6. Do not use temporary generators to power fixtures. | |
7. Assess cable layout to comply with bend radius guidance in Installation Instructions. Do not over bend cables. | |
8. Fully latch all connectors per Installation Instructions. Attach end terminator to last fixture if required. Do not allow unmated connectors to be exposed to water. | |
9. Install proper Surge Protection Devices. Contact a qualified professional for guidance. List surge protection devices (including lightning protection systems). Describe the surge protection installation method on this project. | |
10. Properly seal all junction boxes and Power Data Supplies per Installation Instructions. What kind/type of junction boxes are installed and what sealing methods have been used? | |
11. Attach appropriate safety cable tether per Installation Instructions for raised fixtures. What is the maximum height fixtures are installed? Please list what is directly below fixtures. |